Welding of Geberit pipes

Guide to the installation of Geberit drainage pipes by welding

Geberit polypropylene pipes for drainage systems are mounted using several processes:

  • Electrofusion sleeve coupling;
  • Butt welding.

Pipe welding: General Information

Butt welding is the simplest method of installing Geberit pipes, and this method of connection does not require the use of additional components.

The Geberit pipes with diameters from 90 mm are welded with using Geberit Universal or Media welding machines. The Geberit pipes with diameter up to 75 mm can be welded by hand.

The table below shows the approximate parameters for the welding of the Geberit Silent-db20 and HDPE pipes.

 

Pipe Welding allowance per weld seam Heating up time Time until full pressure buildup Welding and cooling time Welding pressure
  Silent-db20 HDPE Silent-db20 HDPE Silent-db20 + HDPE Silent-db20 + HDPE Silent-db20 + HDPE
DN, mm cm cm sec sec sec min N
56 0,3 0,3 45 40 4 3 80
63 0,3 0,3 45 40 4 3 90
75 0,4 0,3 50 40 4 4 100
90 0,5 0,4 70 50 5 5 150
110 0,6 0,5 85 63 5 5 220
125 0,5 71 5 5 280
135 0,6 90 5 5 280
160 0,8 0,7 110 92 5 5 450
200 0,7 100 5 5 570
250 0,8 110 5 5 900
315 1,0 140 6 6 1400

 

For reliable welding of Geberit pipes you should observe the following:

  • Ambient temperature: -10 °C to +40 °C;
  • Clean welding plate surface;
  • Temperature of the welding plate should be +220° C;
  • You should monitor the color of the warning light - it should be green.

Creating butt welding manually

1. The Geberit pipe is cut to the required length - the pipe is cut at right angles to the pipe axis, then the ends should be cleaned.

2. The ends of the pipes are pressed lightly on the plate and heated.

3. When heated, the ends of the pipes are held in such a way that they warm up evenly.

4. After welding beads form, the ends are pushed together.

Manual butt welding

5. The welding pressure rises to the recommended value.

6. Examine the butt welding.

Important! Cooling the joint can not be accelerated by cold objects or water.

Result of manual welding

Creating butt welding by machine

1. In the welding machine the ends of pipes or fittings are clamped - the Geberit pipes are cut to the right size at right angles and deburred.

2. Then you need to tear off the ends.

3. The ends of the pipes are slightly pressed on the plate and held so that they are evenly heated.

4. The welding plate is removed and then immediately push the pipe ends together.

5. After that, smoothly increase the welding pressure to the reference value.

6. After cooling of the joint, the pipe assembly is released.

7. Examine the butt welding.

The result of welding with the machine

Creating an electrofusion sleeve coupling welding joint

Indicators Geberit ESG 3

For creating an electrofusion sleeve coupling welding joint you will need:

  • Geberit electrofusion sleeve coupling;
  • The Geberit electrofusion welding machine ESG 3 (the working elements of the ESG 3 are shown in the figure).

Electrofusion welding is carried out under the following conditions:

  • Permissible ambient temperature: -10 °C to +40 °C;
  • The electrofusion welding machine ESG 3 is connected to a network with voltage of 110-240 V / 50-60 Hz;
  • The welding process should be monitored carefully;
  • Before the start of work, you must stop the water sweating in the pipeline and dry the electrofusion sleeve coupling and the pipeline

According to the rules, electrofusion welding is performed only 1 time.

1. The Geberit pipes are cut to the required size, the outer surface is thoroughly cleaned.

2. A section of the Geberit pipe or fitting which will be inserted into the electrofusion sleeve coupling is cleaned with a blade or scraper.

Зачистка трубы скребком на 3 см

3. The depth of the insert is 3 cm.

4. The Geberite pipe or fitting is inserted into the electrofusion sleeve coupling, the depth of the insert is checked so that the axes of the welded ends are not coaxial.

5. The electrofusion welding machine is connected to the mains, after which the wire is connected to the electrofusion sleeve coupling or electrofusion tape, and it can be connected only after the coupling is installed on the pipe / fitting.

6. When everything is ready, you should press the start button - the welding will be completed in about 80 seconds, as indicated by the moving yellow indicator.

Important! When welding and cooling the connection point, you should not touch the pipeline or the electrofusion sleeve coupling.

Creating electrofusion coupling with integrated thermal fuse welding joint

Important! One electrofusion coupling with integrated thermal fuse welding joint can only be used for welding once.

The electrofusion coupling with integrated thermal fuse welding joint is used with a different extension wire than using with conventional Geberit electrofusion coupling and electrofusion tapes, so before starting work you must ensure that the correct wire is connected.

1. The pressure rings are put on the pipes - when the welding is completed the rings are removed, but not earlier than 15 minutes after the end of the work.

2. Pipes are cut to the required length, and then they are cleaned thoroughly.

Зачистка трубы скребком на 10 см

3. The surface of the pipe or fitting that will be inserted into the electrofusion coupling is cleaned with Geberit scraper, only the uppermost oxide layer is removed.

4. All burrs are removed, the chamfer is removed from the ends of the pipes.

5. The depth of the insert is 7.5 cm.

6. Pipes / fittings are inserted into the electrofusion coupling with integrated thermal fuse welding joint, after which it is necessary to check the depth of the insert, while the axes of the welded ends must not coincide.

7. The electrofusion welding machine is connected to the network, at the same time the connecting wire is connected to the electrofusion coupling.

8. The start button is pressed - after start of work the button "welding" should be lighted. As soon as the signal button goes out, the welding process will be completed (approximately 7 minutes).

9. After 15 minutes after the welding is completed, the insulating film is removed.